Maître d’ouvrage :
KHOURY Contracting Compagnie
Mission : Design and built (Etudes) Protection plage (Liban)
Début : 30/03/2015
Adjudicataire :
CORINTHE Ingénierie
Montant : 28 125 euros TTC
KHOURY Construction Contracting : Mission d’étude d’exécution protection de plage
The mission awarded to CORINTHE Engineering is to design a submerged breakwater to reduce the energy from the waves offshore before the waves reaches the onshore section. This will stop the submersion on the beach during storms such as the one which occurred on January 2015 the 6-7th.
The mission is extended to a part time supervision of the works.
The design mission is divided as follows:
• Review data collecting
• Wave propagation
• Diagnostic of the site and layout of the proposed solutions
• Beach evolution numerical modelling
• Detailed design of the solution
This report is about « Diagnostic of the site and layout of the proposed solutions » and « Beach evolution numerical modelling ».